Dehradun: Reviewing the progress of three major projects in the state—the Haridwar Ganga Corridor, Rishikesh Ganga Corridor, and Sharda Riverfront Corridor—Chief Minister Pushkar Singh Dhami has directed officials to accelerate construction work. He stated that projects ready for launch should have their necessary procedures completed swiftly so work can begin, adding that progress on several projects should be visible on the ground within the next month.
At the fifth meeting of the Uttarakhand Investment and Infrastructure Development Board held at the Chief Minister’s residence on Friday, the Chief Minister reviewed the physical and financial progress of the projects. He instructed officials to ensure that development plans preserve each region’s distinct identity, local culture, religious significance, and natural features, which will also boost tourism and employment prospects.
During the meeting, it was informed that projects worth ₹3,297 crore are proposed under the Haridwar Ganga Corridor, with works worth approximately ₹495 crore currently in the implementation phase. Work on the administrative route is 75 percent complete, the northern area of Har Ki Pauri is 70 percent complete, redevelopment of Har Ki Pauri and Subhash Ghat is 50 percent complete, and work in the Rodi Belwala area has reached 45 percent. Approach roads to Maa Mansa Devi and Maa Chandi Devi temples are 55 percent and 50 percent complete, respectively. These works are targeted for completion by December 2026, while 30 percent of the redevelopment of Satikund has been completed and is scheduled for completion by April 2027.
Under the Rishikesh Ganga Corridor, projects worth ₹3,456 crore are proposed, with works worth ₹274 crore currently underway. Construction of the Integrated Command and Control Center near Janki Jhula is 39 percent complete and is targeted for completion by June 2027. Additionally, development of Triveni Ghat at ₹115.07 crore, beautification of Astha Path at ₹35.78 crore, and construction of the Chandrabhaga pedestrian bridge at ₹32.28 crore are underway, alongside the development of rafting and tourist facilities at Shivpuri and Neem Beach.
Under the Sharda Riverfront Corridor, projects worth ₹1,526 crore are proposed, with works worth ₹340.49 crore in the implementation phase. Seventy-five percent of the ecological corridor being developed at a cost of ₹85.23 crore to reduce disaster risks has been completed. Redevelopment of Sharda Ghat at a cost of ₹184.20 crore is 30 percent complete, and the first phase of the ₹66.49 crore urban drainage scheme is 13 percent complete, while construction of the Tanakpur bus terminal is in its final stage.
The meeting noted that projects totaling ₹8,279 crore are proposed across the three corridors, of which works worth around ₹1,109 crore are currently under implementation. These projects are estimated to generate direct employment for 21,000 to 27,000 people and indirect employment for 45,000 to 53,000 people.
In addition, progress was shared on the plan to develop a Spiritual Economic Zone on approximately 72 hectares of land in the Srinagar–Belkedar area. Proposals related to the safe and well-planned development of adventure tourism, expansion of tourist amenities, private investment, and project monitoring were also discussed at the meeting.
Cabinet Ministers Satpal Maharaj and Pradeep Batra, Infrastructure Monitoring Council Vice Chairman Vishwas Dabar, Chief Secretary Anand Bardhan, along with government officials and representatives of concerned executing agencies, were present at the meeting.